Work started on Spital Hill and Ellesmere Green

Upgrade of Spital Hill footway & improvements to Ellesmere Green– Traffic Management Arrangements

The Council’s appointed contractor, Amey, has started work to improve the footways on Spital Hill and Ellesmere Green.

A one-way traffic system has been agreed, with traffic going up Spital Hill (similar to what was done when Tesco was being built, as well as the Relief Road).

Dates of traffic management:

There is a diversion route for those travelling down Spital Hill. This is via Gower Street and Sutherland Street back to Savile Street. Hallcar Street and Earsham Street remain unaffected.

Work will take place during the day.

Please note that Ellesmere Green will be fenced off from mid-October until the work is complete (February 2014).

Order of works:

This document was last modified on 2013-10-17 15:47:00.