Repairs to the main streets in Burngreave will begin in June.
The schedule of road resurfacing is listed below. During these times, the whole road may be closed and traffic will be diverted. Most of the work will take place at night, between 7pm and 6am, however roads will remain open during the day.
Letters to residents
For residents, there will be no on-street parking and limited access to properties during these hours. Residents will receive individual letters about two weeks before the closure and temporary road signs will go up about 5 days before the work starts.
The work will include installing new LED street lighting, drainage and new surfaces to pavements and roads.
Burngreave Road
Burngreave Road will be closed between 24th and 31st July, with traffic diverted around Scott Road and Ellesmere Road, which may cause significant delays.
The work schedule is heavily dependent on the weather and can be affected by unforeseen circumstances, so the schedule may change at short notice. Look out for temporary signs on the roads for updated information.
For a map of the works and further info can be found on the Council’s website: www.sheffield.gov.uk/roads or follow a link from the Messenger website. Contact Streets Ahead on 273 4567
Resurfacing schedule
Owler Lane
Tuesday 25 – Wednesday 26 June
Rushby Street & Owler Lane
Thursday 27 June – Wednesday 3 July
Carlisle Street East
Thursday 4 July – Tuesday 9 July
Carlisle Street
Wednesday 10 July – Thursday 11 July
Sutherland Street
Friday 12 July – Tuesday 16 July
Gower Street
Wednesday 17 July – Sunday 21 July
Spital Hill
Monday 22 July – Tuesday 23 July
Burngreave Road
Wednesday 24 July – Wednesday 31 July