The Council has revealed the timetable for Burngreave’s streets to be repaired under the £2 billion PFI contract. The first streets to be done are in Shiregreen.
Burngreave Rd, Spital Hill and Owler Lane are due to be repaired in April to June 2013 and Page Hall will see improvements in 2014 but Barnsley Rd will not be worked on until 2016.
Before then, all the roads on the town side of Burngreave Rd will be completed (2015) but the rest of Burngreave will have to wait until 2017.
Street-by-street detail is available on an online map at https://www.sheffield.gov.uk/roads/works/schemes/streetsaheadproject/works-sch edules/ works-map.html