Partnership Board Meeting – Wednesday, 21 December 2005

Advancing Together Update

What was discussed

The Partnership Board were pleased to welcome Sir Robert Kerslake and Jonathan Crossley-Holland from Sheffield City Council (SCC) who gave members an update on the progress of the projects contained in the Advancing Together Agreement between Burngreave New Deal for Communities (BNDfC) and SCC. Members discussed the issues and challenges we need to address together as we move into a new phase of the programme.

What we decided

To instruct the BNDfC Chief Executive to progress work required regarding mainstreaming. The Advancing Together Agreement is now at a stage where projects are winding down we need to embed the initiatives that have worked, capture the important elements, reprioritise resources and look at new ways of delivery. The Chief Executive should feedback information to SCC on this subject.

Woodside

What was discussed

Members discussed the options identified in 2003 for the reinvestment of the funding used for the accelerated demolition of the Woodside estate.

What we decided

To request SCC undertake an independent valuation of the site by 31st January 2006. To request that a report be presented to the February 2006 Partnership Board meeting for a decision to be made on options 1, 2 and 3 identified in the report. To request the Chief Executive to report back on the role of the Partnership Board in the development of the Woodside brief.

AT Transformational Projects Update

What was discussed

Board members discussed the progress of the Transformational Projects contained within the Advancing Together Agreement between BNDfC and SCC.

What we decided

To approve the Vestry Hall tender from Simpsons (York) for the sum of £2,199,516.48. To endorse the decision of the Advancing Together Transformational Projects Steering Group to re-tender the Sorby House project.